The monolith of the first floor is completed in the second section, the floor slab is being made

April 09, 2024

Real Estate Corporation RIEL and Bosphorus Development report that the construction of the Maxima Residence RC continues. According to the project manager, the first floor monolith is completed in the second section, the floor slab is being made, reinforced concrete monolithic stairs are being installed, and ventilation units are being installed.

In the first section, the floor of the fifth floor has been completed, the vertical of the sixth floor is being poured, and reinforced concrete monolithic stairs and ventilation units are being installed in parallel. Preparations for the masonry walls have begun.

In the parking lot, the monolith of the first bay of the first section has been completed, and the transformer substation has been prepared.

At the same time, the pile field is being constructed in the third section, with 40% readiness. The specialists also installed a tower crane.

A sales office has been completed next to the construction site.

You can always find out about the purchase of apartments in Maxima Residence RC and the complex construction progress in the company’s sales department. Contacts are available at the link.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Join our social networks
Contact us in convenient way
(044) 321-10-70
Feedback
The exchange rate as of 11/23/2024 is 41.37 UAH.
Sales departments
Kyiv, str. Konovaltsya, 30
Kyiv, 56, Ukrainian Air Force avenue
© 2024  Maxima Residence. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.