Monolithic structures of -1 floor are being built in the second section

February 09, 2024

Real Estate Corporation RIEL and Bosphorus Development report that the construction of Maxima Residence RC continues. According to the project manager, in the second section the construction of -2 floor has been completed, waterproofing works and construction of monolithic structures of -1 floor continue. Specialists are preparing for the installation of the tower crane.

Vertical of the third floor is performed in the first section, installation of staircases and ventilation blocks, arrangement of monolithic stairs and masonry walls of the basement floor are in progress. Waterproofing of the underground part of the building has been completed and backfilling has been carried out.

In parallel, the construction of load-bearing wall on the side of the neighboring housing estate is completed in the third section.

In the parking lot (the first section) - the floor slab is ready, the transformer substation room is being arranged.

You can always find out about the purchase of apartments in Maxima Residence RC and the complex construction progress in the company’s sales department. Contacts are available at the link.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Join our social networks
Contact us in convenient way
(044) 321-10-70
Feedback
The exchange rate as of 12/3/2024 is 41.66 UAH.
Sales departments
Kyiv, str. Konovaltsya, 30
Kyiv, 56, Ukrainian Air Force avenue
© 2024  Maxima Residence. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.