In the first section, the vertical elements of the second floor are being erected

December 11, 2023

Real Estate Corporation RIEL and Bosphorus Development report that the construction of Maxima Residence RC is in progress. According to the project manager, the first floor in the first section has been completed, and the construction of the vertical elements of the second floor is underway.

In the second section, we began to reinforce the first section of the vertical elements of -2 (basement) floor.

At the same time, a pile field is being built in the third section.

In the parking lot (first pour object) – vertical elements at the level of -2 floor have been performed.

You can always find out about the purchase of apartments in Maxima Residence RC and the complex construction progress in the company’s sales department. Contacts are available at the link.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Join our social networks
Contact us in convenient way
(044) 321-10-70
Feedback
The exchange rate as of 11/21/2024 is 41.35 UAH.
Sales departments
Kyiv, str. Konovaltsya, 30
Kyiv, 56, Ukrainian Air Force avenue
© 2024  Maxima Residence. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.