Laying of external and internal walls in the first section continues
RIEL Real Estate Corporation and Bosphorus Development report that the construction of the Maxima Residence RC continues. According to the project manager, the laying of exterior and interior walls in the first section is underway, and has already been almost completed on five residential floors. At the same time, the vertical monolithic elements of the 13th floor are being arranged, and the installation of precast concrete monolithic stairs and ventilation units continues. Backfilling is completed.
In the second section, the vertical elements of the seventh floor are being arranged, the laying of walls on residential floors continues, and the tower crane is being positioned. The installation of ventilation units and reinforced concrete monolithic stairs continues.
All the piles in the parking lot have been installed.
In the third section, the pile field has been completely completed.